(8) Given the following values for AC, PV, and EV along with

(8) Given the following values for AC, PV, and EV along with the Critical Ratio Limit Chart, answer the following questions: AC = $7373 PV = $15, 975 EV = $9585 a. Determine the Critical Ratio for this project. b. Given the Critical Ratio Limit Chart, determine what actions, if any, are required.